CX-035902: APCo WV Resilience and Reliability Project

At the project locations in southern West Virginia (including Clay, Nicholas, Raleigh, Fayette, Kanawha, McDowell, Wyoming, Lincoln, Mingo, and Boo…

Office of NEPA Policy and Compliance

June 3, 2026
Estimated Read Time   min

At the project locations in southern West Virginia (including Clay, Nicholas, Raleigh, Fayette, Kanawha, McDowell, Wyoming, Lincoln, Mingo, and Boone Counties), the proposed work consists of field-based upgrades to existing electric distribution infrastructure. Activities are focused on construction, installation, and modification of physical system components to improve access, redundancy, and automated operation. 

  1. Tie lines with Distribution Automation Circuit Reconfiguration (DACR) 
  2. DACR projects deploying automatic sectionalizing and fault isolation technologies, 
  3. Line relocation for infrastructure hardening and improved accessibility.