On May 21, 2026, Department of Energy (DOE) issued emergency DOE Order No. 202-26-25, pursuant to section 202(c) of the Federal Power Act, for Unit 4 at the Wagner Generating Station. The order authorizes PJM Interconnection, L.L.C. (PJM), in coordination with the Talen Energy Corporation, to run Unit 4 at the Wagner Generating Station in Anne Arundel County, Maryland to meet anticipated electricity demand. This order is in effect beginning on May 22, 2026 and continues until August 19, 2026.

Date of DocumentSubmitterDocument Title
May 21, 2026PJM Interconnection, L.L.C. (PJM)PJM's 202(c) Application
May 21, 2026PJM Interconnection, L.L.C. (PJM)PJM's 202(c) Application Exhibit A
May 21, 2026Department of EnergyDOE 202(c) Order No. 202-26-25 PJM