DOE/EA-2291: Mitigation Action Plan (March 2026)

DOE's BPA issued a mitigation action plan for the South of Tri-Cities Reinforcement Project (DOE/EA-2291).

Office of NEPA Policy and Compliance

March 13, 2026
minute read time

South of Tri-Cities Reinforcement Project; Benton County, Washington

Bonneville Power Administration (BPA) issued a mitigation action plan (MAP) for South of Tri-Cities Reinforcement Project (DOE/EA-2291) to mitigate the potential environmental impacts of construction of a new 500/115-kilovolt (kV) substation and 18-mile-long 115-kV transmission line in Benton County, Washington. 

For more information, see South of Tri-Cities Reinforcement Project.