CX-034725: Miracle Mile-Snowy Range No. 1 115-kV and Miracle Mile-Snowy Range No. 2 230-kV Structure Replacements, Access Road and Transmission Line Right-of-Way Maintenance, and Gate Replacements

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to conduct routine access road and transmission line right-of-way (…

Office of NEPA Policy and Compliance

October 28, 2025
minute read time

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to conduct routine access road and transmission line right-of-way (ROW) maintenance, and replace existing structures and gates on the on the Miracle Mile-Snowy Range No. 1 (MM-SNG-1) 115-kV and Miracle Mile-Snowy Range No. 2 (MM-SNG-2) 230-kV Transmission Lines in Carbon and Albany Counties, Wyoming. Routine maintenance of existing access roads, crossings, landings, and other ROW features will be completed as necessary within approved work areas to facilitate safe access to the transmission line.