Modification

Description

Modification 001Increase funding in the amount of $500,000.00 on CLIN 00001 from $10,000.00 to $510,000.00. Increase total obligated funding in the amount of $500,000.00 from $10,000.00 to $510,000.00. Change the Contracting Officer from Dustin Dalton to Sylvia Maroney.
Modification 002Change the Contracting Specialist from Sylvia C. Maroney to Terri Harris, and change the Contracting Officer and Invoice Approving Official from Sylvia C. Maroney to Edward A. Bauser.
Modification 003Incorporate the FAR Deviation text in Section I.55 of the contract as included in the attached Civilian Agency Acquisition Council (CAAC) Letter 2021-03, dated September 30, 2021.
Modification 004Change the Contracting Officer and Invoicing Approval Official
Modification 005

Supplemental Agreement for Work Within Scope.  Realignment of Section B, and revise SOW to align task orders within the SOW.

Modification 006Supplemental Agreement for Work Within Scope.  Extend the Period of Performance and Increase the Ceiling Value.