Substation Preventive Maintenance ProgramCX(s) Applied: A1, A9, B1.3, B5.1Date: 08/26/2010Location(s): Ottawa, OhioOffice(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory
Office of NEPA Policy and Compliance
August 26, 2010Substation Preventive Maintenance Program
CX(s) Applied: A1, A9, B1.3, B5.1
Date: 08/26/2010
Location(s): Ottawa, Ohio
Office(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory
Upgrade the 26 year old substation to enhance the reliability of the electrical system and increase safety for workers and residents.