CX-003527: Categorical Exclusion Determination

Toussaint-Benton 12.47 Kilovolt Distribution Circuit UpgradeCX(s) Applied: A1, A9, B1.7, B4.13, B5.1Date: 08/26/2010Location(s): Oak Harbor, OhioOffice(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory

Office of NEPA Policy and Compliance

August 26, 2010
Estimated Read Time   min

Toussaint-Benton 12.47 Kilovolt Distribution Circuit Upgrade
CX(s) Applied: A1, A9, B1.7, B4.13, B5.1
Date: 08/26/2010
Location(s): Oak Harbor, Ohio
Office(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory


Replace approximately 1.2 miles of the main distribution line. This process will include replacing all wooden structures and two aging sectionalizers and installing a new 336 aluminum conductor, steel reinforced (ACSR) and equipments.