CX-003082: Categorical Exclusion Determination

Demolition of Buildings 11-10 and 11-30CX(s) Applied: B1.23Date: 07/07/2010Location(s): Amarillo, TexasOffice(s): NNSA-Headquarters, Pantex Site Office

Office of NEPA Policy and Compliance

July 7, 2010
Estimated Read Time   min
Demolition of Buildings 11-10 and 11-30
CX(s) Applied: B1.23
Date: 07/07/2010
Location(s): Amarillo, Texas
Office(s): NNSA-Headquarters, Pantex Site Office

The U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA), proposes to demolish Buildings 11-10 and 11-30 at the Pantex Plant. The overall objectives are to reduce Plant maintenance costs and reduce the Pantex Plant footprint by 3,144 square feet.