CX-017535: L0360- Cougar-Thurston Number 1 Impairments and Holden Creek Substation Interconnection

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

January 18, 2018
Estimated Read Time   min

The Bonneville Power Administration proposes to interconnect the Cougar-Thurston No. 1 115-kilovolt transmission line to Eugene Water and Electric Board’s new Holden Creek Substation. To interconnect the substation, Bonneville Power Administration would install a glue-laminated wood pole structure approximately 80 feet back-on-line from structure 28/1.