CX-001383: Categorical Exclusion Determination

Building 212 Electron Microscopy ImprovementsCX(s) Applied: B2.1Date: 04/05/2010Location(s): IllinoisOffice(s): Science, Argonne Site Office

Office of NEPA Policy and Compliance

April 5, 2010
Estimated Read Time   min

Building 212 Electron Microscopy Improvements
CX(s) Applied: B2.1
Date: 04/05/2010
Location(s): Illinois
Office(s): Science, Argonne Site Office

 

This project will demolish the existing heating, ventilating, and air conditoning (HVAC) systems within the D Wing of Building 212 (Electron Microscopy Area). Included in this demolition are 5-fancoil units and associated duct work, and duct work missing boxes. These items would be replaced by a new low-sound and specifically designed and built 30-ton air handling unit, insulated sound suppressing supply and return ductwork, and all necessary piping, valves, and sound reducing insulation. Silencers and laminar flow registers, controls, air balancing and commissioning are also included in this work.

 