CX-005362: Categorical Exclusion Determination

San Emidio Geothermal Power Plant Energy Efficiency UpgradesCX(s) Applied: B3.7, B5.1Date: 03/02/2011Location(s): Washoe County, NevadaOffice(s): Loan Guarantee Program Office

Office of NEPA Policy and Compliance

March 2, 2011
Estimated Read Time   min
San Emidio Geothermal Power Plant Energy Efficiency Upgrades
CX(s) Applied: B3.7, B5.1
Date: 03/02/2011
Location(s): Washoe County, Nevada
Office(s): Loan Guarantee Program Office

The project is comprised of two phases to provide a nominal 17.2 megawatts (MW) of renewable energy electric power. Phase 1 would involve the completion of a repowering action to replace an existing 2.5 MW net geothermal power unit with a nominal 8.6 MW power unit using existing production and injection wells. Phase 2 would involve installation of an additional nominal 8.6 MW geothermal repowering unit, and drilling of 3 new geothermal production wells and up to two new injection wells.