CX-000830: Categorical Exclusion Determination

Construct Rail Spur to Concrete Batch Plant, P-AreaCX(s) Applied: B1.13Date: 08/31/2009Location(s): Aiken, South CarolinaOffice(s): Environmental Management, Savannah River Operations Office

Office of NEPA Policy and Compliance

August 31, 2009
Estimated Read Time   min
Construct Rail Spur to Concrete Batch Plant, P-Area
CX(s) Applied: B1.13
Date: 08/31/2009
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office

Install railroad spurs into P-Area Facility to new batch plant (see EEC ARRA-P-2009-033) to support the closure activities of P and R Operable Units. Revision 1 includes the use of pesticide/herbicide. Herbicide will be applied to existing vegetation in the planned railroad bed area. No endangered species will be impacted. Herbicide will be applied in accordance with the Site Herbicide program.