Flowline Leak at 68-66-SX-34CX(s) Applied: B5.2, B5.4Date: 02/01/2010Location(s): Casper, WyomingOffice(s): RMOTC
Office of NEPA Policy and Compliance
February 1, 2010Flowline Leak at 68-66-SX-34
CX(s) Applied: B5.2, B5.4
Date: 02/01/2010
Location(s): Casper, Wyoming
Office(s): RMOTC
Elimination of the flowline at 68-66-SX-34. Dig up and locate leak. Take oil-contaminated soil to land farm and record in log book. The duration of this project will be approximately 4-days. The equipment to be used is as follows: backhoe and welder. We will be eliminating the flowline and pumping to a tank set on location.