Geothermal Technologies ProgramCX(s) Applied: B4.12Date: 07/09/2010Location(s): Casper, WyomingOffice(s): RMOTC
Office of NEPA Policy and Compliance
July 9, 2010Geothermal Technologies Program
CX(s) Applied: B4.12
Date: 07/09/2010
Location(s): Casper, Wyoming
Office(s): RMOTC
Install power line from existing pole on the section 21 drilling pad to the location for the pump to withdraw water from the Little Teapot Creek for the geothermal project at the North Waterflood Facility building. For the most part, the line will be trenched in and will follow an existing road. The potential exists for the disturbance of cultural artifacts during the excavation of virgin ground.