Dworshak-Taft Insulator Replacement, Mile 76 to Mile 89 CX(s) Applied: B1.3Date: 42565 Location(s): Multiple LocationsOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
July 14, 2016Dworshak-Taft Insulator Replacement, Mile 76 to Mile 89
CX(s) Applied: B1.3
Date: 42565
Location(s): Multiple Locations
Offices(s): Bonneville Power Administration
Bonneville Power Administration proposes to replace insulators at 15 structure locations along the Dworshak-Taft No. 1, 500-kilovolt transmission line from mile 76 to mile 89.