CX-014178: Categorical Exclusion Determination

Chief Joseph-Foster Creek Underground Fiber Optic Cable Installation CX(s) Applied: B4.7Date: 09/14/2015 Location(s): WashingtonOffices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

September 14, 2015
Estimated Read Time   min

Chief Joseph-Foster Creek Underground Fiber Optic Cable Installation
CX(s) Applied: B4.7
Date: 09/14/2015
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration proposes to install approximately 0.5 mile of underground fiber optic cable between BPA’s Chief Joseph Substation and Douglas County Public Utility District’s Foster Creek Substation.

Document(s) Available for Download