Oneida Indian Nation Community-Scale Clean Energy Deployment Combined Heat and Power Project Award Number: DE-EE0006944 CX(s) Applied: A9, B5.14 Tribal Energy Program Date: 05/29/2015 Location(s): NY Office(s): Golden Field Office
Office of NEPA Policy and Compliance
May 29, 2015Oneida Indian Nation Community-Scale Clean Energy Deployment Combined Heat and Power Project
Award Number: DE-EE0006944
CX(s) Applied: A9, B5.14
Tribal Energy Program
Date: 05/29/2015
Location(s): NY
Office(s): Golden Field Office
The Oneida Indian Nation (Nation) would utilize DOE and cost share funding to upgrade and improve the operation of the Nation’s Central Utility Plant (CUP) by installing a two-stage Back Pressure Steam Turbine (BPST). The proposed project activities include the design, acquisition, installation, commissioning and testing of the BPST. The CUP is located on the campus of the Turning Stone Resort (opened in 1993) located at 5218 Patrick Road, Verona, NY 13478.