CX-033666: Establish Preventive and Predictive Maintenance to Enhance Grid Resilience in Fort Pierce
This project will involve the installation of 408 fault indicators and 18 automatic switches across 34 distribution feeders within the Fort Pierce …
Design and development of a Microgrid Resiliency Station to be constructed near the Spokane Tribal Administrative Offices. This project will includ…
The project focuses on enhancing grid resilience through infrastructure upgrades, including hardening critical facilities, integrating and improvin…
Upgrading the SRS technological infrastructure by installing underground fiber optic cable at various locations across the site.…
BPA proposes to allow AT and T to upgrade their wireless equipment at an existing telecommunications tower located within BPA’s Port Angeles Substa…
Troy Power and Light plans to replace old electric meters with new smart meters, attaching repeaters to existing power poles to establish a network…
UMass Amherst plans to upgrade the campus's existing medium voltage electric distribution system through the installation of five Automatic Transfe…
The project scope includes replacing approximately five circuit miles of outdated copper powerline conductor with new aluminum conductor. This proj…
Installation of long duration battery energy storage system (LD-BESS), grid-forming inverter, charge controller, and all necessary electrical equip…
Construct 0.76 mi. of 3-phase line to connect two circuits. Install a 3000kVa transformer to connect two circuits. Convert 1.5 mi. of 1-phase lin…