The U.S. Department of Energy (DOE) is proposing to provide funding to the Little Rock School District to perform energy efficiency upgrades at 15 schools within their district. This funding opportunity is part of a DOE prize competition known as FY24 Renew America's Schools - Prize to Cooperative Agreement.
The transmission line will be upgraded to 161kV. The transmission line will be constructed within the existing transmission ROW in both Washington …
The transmission line will be upgraded to 161kV. The transmission line will be constructed within the existing transmission ROW in both Washington …
The project involves removal of approximately 6,900 feet of overhead electrical distribution lines, replacement of 4 platform structures and pad-mo…
Construction of a converter station and an overhead high voltage direct current (HVDC) transmission line in the Nikiski area, a submarine HVCD cabl…
BUECI plans to upgrade existing aged switchgear with modern, better weatherized vacuum circuit breakers and protective relays. The new system will …
Activities include the inspection of circuit 968530 to identify encroaching vegetation. …
Replacement of overhead electric distribution system components, including wires, poles, capacitors, and the addition of new transformers in an old…
Replace ~404 vintage wooden poles across AECC service territory in northeast and northwest Arkansas, exchanging them for weather-resistant steel po…
The city proposes to reconductor 4,922 feet of distribution lines and replace wood electric poles.…