CX-270210: Test Reactor Area (TRA)-670 New Window in Advanced Test Reactor (ATR) Production Control Center

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

July 18, 2016
Estimated Read Time   min

The window in the Production Control Center (PCC) at the Advanced Test Reactor (ATR), building TRA-670, is not operational and a new, functional window is needed. The proposed action would construct a new window to the PCC. The activity would require block removal for installation of a framed opening on the south wall. The new opening would be approximately 39 in. X 32 in. and constructed on a non-load bearing wall. The opening would be framed with finished wood and finished. Glass would not be installed in the new opening.