CX-270099: Test Reactor Area (TRA)-670 Primary Pump Pit Platform

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

February 1, 2016
Estimated Read Time   min

The primary pump pit platforms have clearance issues. There is not enough space in between the hatch wall and the ladder and not enough space between the ladder and the safety rails on the pump pit platform. The purpose of this work scope is to alleviate these clearance issues by adding a new section of platform constructed with the same materials as the old section.