Bonneville Power Administration (BPA) is proposing to replace two failing wood pole structures and associated hardware in BPA’s Olympia District, s…
Office of NEPA Policy and Compliance
September 16, 2026Bonneville Power Administration (BPA) is proposing to replace two failing wood pole structures and associated hardware in BPA’s Olympia District, specifically Olympia-St. Clair No. 1 1/1 and 1/2. The work would include removing the existing wood pole structures and replacing them in kind in the same locations. Approximately 300 feet of new access roads would be required to access the structures. Two 50x50 foot landings would be created at each structure. Fire wraps would also be added. No helicopter use would be required.