CX-035933: FY21 North Bend Pole Replacement and Access Road Project (Update to previous CX determination issued on May 13, 2025)

Bonneville Power Administration (BPA) is proposing to replace 3 deteriorating wood pole structures and associated hardware and guy wires on the Wen…

Office of NEPA Policy and Compliance

June 17, 2026
Estimated Read Time   min

Bonneville Power Administration (BPA) is proposing to replace 3 deteriorating wood pole structures and associated hardware and guy wires on the Wendson-Tahkenitch No. 1 transmission line and the Rogue-Gold Beach No. 2 lines. This CX determination has been updated to reflect changes in project design, specifically new access road work, equipment landings, and culvert installation.