WAPA is finishing the rebuild of Great Falls to Verona 161 kV. The rebuild will use 230 kV wood and Glued Laminated structures and add OPGW. Ther…
Office of NEPA Policy and Compliance
November 14, 2025WAPA is finishing the rebuild of Great Falls to Verona 161 kV. The rebuild will use 230 kV wood and Glued Laminated structures and add OPGW. There are a number of reroutes within the sections that will be rebuilt with eventual 230kV operation. This CX is for Phase 3, which includes structures 66/5 to 79/3 (Approx 12.8 miles).