This activity is for completing a safe shutdown and deactivation process for F/H Lab (772-F, 772-1F and 285-3F). This process is required to prepar…
Office of NEPA Policy and Compliance
September 24, 2025This activity is for completing a safe shutdown and deactivation process for F/H Lab (772-F, 772-1F and 285-3F). This process is required to prepare the facility for D and D in the out years. This will involve removing unused chemical and sample returns, removal of combustibles to the greatest extent possible, reducing Material at Risk (MAR), isolating electrical power, diesel power and utilities (steam, water, instrument air, argon and compressed gasses).