Replacement of existing reclosers with new vacuum reclosers, Addition of auto-source transfer equipment on our existing distribution lines to impro…
Office of NEPA Policy and Compliance
May 15, 2025Replacement of existing reclosers with new vacuum reclosers, Addition of auto-source transfer equipment on our existing distribution lines to improve system reliability, Redundancy and reconfiguration of equipment within existing substations, Engineering and relay coordination studies to support the activities listed above. Project work to occur at four existing substations: Fort Hill, Listonburg, Markleton, and Mason Dixon substations.