CX-033440: Denver High School Microgrid for Community Resilience

Installation of long duration battery energy storage system (LD-BESS), grid-forming inverter, charge controller, and all necessary electrical equip…

Office of NEPA Policy and Compliance

March 13, 2025
Estimated Read Time   min

Installation of long duration battery energy storage system (LD-BESS), grid-forming inverter, charge controller, and all necessary electrical equipment and controls to integrate the LD-BESS into the existing building electrical systems, including the existing rooftop solar array. The installation is expected to include minor excavation for necessary foundation for the LD-BESS and any required enclosure(s), as well as for any electrical conduit or other equipment needed between the building and the LD-BESS location.