CX-030375: Install Two Additional DeltaV Workstations in the Building 233-H Central Control Room

Per modification traveler MT-TRI-2024-00002, two additional unclassified DCS workstations are required to be installed in the Building 233-H Centra…

Office of NEPA Policy and Compliance

March 4, 2024
minute read time

Per modification traveler MT-TRI-2024-00002, two additional unclassified DCS workstations are required to be installed in the Building 233-H Central Control Room (CCR) prior to the replacement of the General Services programmable logic controller (PLC) under YCON-14. The PLC controls and monitors the 233-H HVAC system, the 249-H cooling tower system and the 249-H HVAC chilled water and process chilled water pumps.