CX-020968: Implement Federal Energy Regulatory Commission (FERC) Recommendations - Par Pond Dam

Install riprap on the upstream slope of Par Pond Dam between the existing riprap and the guard rail. The approximate width of the riprap addition i…

Office of NEPA Policy and Compliance

October 16, 2019
minute read time

Install riprap on the upstream slope of Par Pond Dam between the existing riprap and the guard rail. The approximate width of the riprap addition is 8' and the length is 4470'.