CX-020552: Covington Substation Pedestrian Sidewalk Replacement

The existing pedestrian walkway in front of the Covington Untanking Tower would be replaced due to some cracks causing safety hazards. The entire 1…

Office of NEPA Policy and Compliance

September 4, 2019
minute read time

The existing pedestrian walkway in front of the Covington Untanking Tower would be replaced due to some cracks causing safety hazards. The entire 10’W x 75’L walkway from the parking lot up to the steps leading to the doorway
would be replaced with similar material to match the existing sidewalk. The corner of the stairway landing has some spalling taking place and repair to the landing would also be completed as part of the project.