CX-020215: Remove Insulation for the Replacement of Steam Trap HPC-TRP-002

Remove, replace, reinstall HPC-TRP-002 (steam trap) associated piping, insulation (non-asbestos). There is an associated presumed asbestos contain…

Office of NEPA Policy and Compliance

May 31, 2019
minute read time

Remove, replace, reinstall HPC-TRP-002 (steam trap) associated piping, insulation (non-asbestos).  There is an associated presumed asbestos containing material (PACM) gasket associated with this job, though there is no intent to disturb the gasket by the disassembly of the steam trap.