CX-018268: Miracle Mile - Platte 115 Kilovolt Transmission Line Crossarm Replacements, Carbon County, Wyoming

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

April 6, 2018
Estimated Read Time   min

Western Area Power Administration proposes to replace deteriorating wood crossarms on its wood H-frame structures along 27.1 miles of its Miracle Mile-Platte 115 kilovolt Transmission Line.