CX-016408: Elmo-Hot Springs Fiber Optic Cable Installation

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

January 5, 2017
Estimated Read Time   min

Bonneville Power Administration proposes to install approximately 22 miles of fiber optic cable between Mission Valley Power’s Elmo Substation and Bonneville Power Administration’s Hot Springs Substation.