10 MWe Coal Direct Chemical Looping Large Pilot Plant: Pre-FEED Study CX(s) Applied: A1, A9, B3.6Date: 08/30/2016 Location(s): OhioOffices(s): National Energy Technology Laboratory
Office of NEPA Policy and Compliance
August 30, 201610 MWe Coal Direct Chemical Looping Large Pilot Plant: Pre-FEED Study
CX(s) Applied: A1, A9, B3.6
Date: 08/30/2016
Location(s): Ohio
Offices(s): National Energy Technology Laboratory
Early engineering design study for coal fueled chemical looping plant. Work also includes pilot operations and research at small pilot level.