Big Eddy-Redmond #1 Wood Pole Replacement (Part 2) CX(s) Applied: B1.3Date: 09/28/2015 Location(s): OregonOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
September 28, 2015Big Eddy-Redmond #1 Wood Pole Replacement (Part 2)
CX(s) Applied: B1.3
Date: 09/28/2015
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to replace 11 deteriorating wood poles on its Big Eddy-Redmond #1 230-kV transmission line to ensure continued operational reliability.
CX(s) Applied: B1.3
Date: 09/28/2015
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to replace 11 deteriorating wood poles on its Big Eddy-Redmond #1 230-kV transmission line to ensure continued operational reliability.