Midway-Canon West 230 Kilovolt Transmission Line Access Road Maintenance El Paso and Pueblo Counties, CO CX(s) Applied: B1.3Date: 04/21/2015 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region
Office of NEPA Policy and Compliance
April 21, 2015Midway-Canon West 230 Kilovolt Transmission Line Access Road Maintenance El Paso and Pueblo Counties, CO
CX(s) Applied: B1.3
Date: 04/21/2015
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
Western Area Power Administration (Western) proposes to conduct routine road maintenance of the access road along approximately 9 .1 miles of Transmission Line between Strncture 161/1 and Western's Midway Substation.