CX-013459: Categorical Exclusion Determination

Idaho Falls (IF)-685 ERV-1 Work Platform CX(s) Applied: B2.5Date: 03/11/2015 Location(s): IdahoOffices(s): Nuclear Energy

Office of NEPA Policy and Compliance

March 11, 2015
Estimated Read Time   min

Idaho Falls (IF)-685 ERV-1 Work Platform
CX(s) Applied: B2.5
Date: 03/11/2015
Location(s): Idaho
Offices(s): Nuclear Energy

The proposed project will construct an elevated work platform around an air handler unit in IF-685. The platform is needed so that maintenance personnel will be able to more easily and safely access the elevated air handler. The project will consist of rerouting existing conduit to follow the air handler surfaces, cutting holes in existing walkway grating to allow for support column pass-through, installing support legs, vibration dampening pads, spreader feet, platform framing, handrails, ladder, ladder support and Fibergate molded fiberglass grating.