Energy Systems Laboratory Process Demonstration Unit Pellet Mill Exhaust Stack Installation CX(s) Applied: B1.31Date: 41877 Location(s): IdahoOffices(s): Nuclear Energy
Office of NEPA Policy and Compliance
August 26, 2014Energy Systems Laboratory Process Demonstration Unit Pellet Mill Exhaust Stack Installation
CX(s) Applied: B1.31
Date: 41877
Location(s): Idaho
Offices(s): Nuclear Energy
The proposed action would install an exhaust stack at Energy Systems Laboratory from the existing Process Demonstration Unit (PDU) pellet mill and connect to existing natural gas supporting the PDU equipment.
CX(s) Applied: B1.31
Date: 41877
Location(s): Idaho
Offices(s): Nuclear Energy
The proposed action would install an exhaust stack at Energy Systems Laboratory from the existing Process Demonstration Unit (PDU) pellet mill and connect to existing natural gas supporting the PDU equipment.