Bayou Choctaw Cavern 20 Decommissioning (Long Term Actions) CX(s) Applied: B1.28 Date: 01/10/2014 Location(s): Louisiana Offices(s): Strategic Petroleum Reserve Field Office

Office of NEPA Policy and Compliance

January 10, 2014
Estimated Read Time   min
Bayou Choctaw Cavern 20 Decommissioning (Long Term Actions)
CX(s) Applied: B1.28
Date: 01/10/2014
Location(s): Louisiana
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall furnish all materials, tools, equipment, supplies, transportation, facilities, labor, supervision and services required to perform long term actions for the decommissioning of Bayou Chocraw Cavern 20. Tasks include isolating the 12" crude oil line, demolition of the 12" crude oil piping, and demolition of the firewater piping. All other tasks will be performed by site personnel.