North Parking Lot High Level Waste Canister Fabrication and Concrete Pad Construction CX(s) Applied: B1.15, B1.23 Date: 09/19/2013 Location(s): New York Offices(s): West Valley Demonstration Project
Office of NEPA Policy and Compliance
September 19, 2013North Parking Lot High Level Waste Canister Fabrication and Concrete Pad Construction
CX(s) Applied: B1.15, B1.23
Date: 09/19/2013
Location(s): New York
Offices(s): West Valley Demonstration Project
Evaluate the additional actions associated with construction and operation of a canister fabrication operation, including installation and subsequent demolition of a concrete pad at the West Valley Demonstration Project.
CX(s) Applied: B1.15, B1.23
Date: 09/19/2013
Location(s): New York
Offices(s): West Valley Demonstration Project
Evaluate the additional actions associated with construction and operation of a canister fabrication operation, including installation and subsequent demolition of a concrete pad at the West Valley Demonstration Project.