CX-011224: Categorical Exclusion Determination

Replacement of Deep-Anode Ground Bed Sites for Big Hill Cavern 104 and Site Unit 1 “A”, and BC Cavern 18 CX(s) Applied: B1.3 Date: 10/01/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

Office of NEPA Policy and Compliance

October 1, 2013
Estimated Read Time   min
Replacement of Deep-Anode Ground Bed Sites for Big Hill Cavern 104 and Site Unit 1 “A”, and BC Cavern 18
CX(s) Applied: B1.3
Date: 10/01/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall provide all materials, tools, equipment, supplies, transportation, facilities, labor, supervision, and services required for the installation of new deep-anode ground bed sites for BH Cavern 104 and Site Unit 1 “A”, and BC Cavern 18. Existing anode beds shall be abandoned in place. Work consists of drilling operations, resistance log of well, component termination, and site cleanup.