105-L Transfer Bay Drainage Repair CX(s) Applied: B1.3 Date: 08/27/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office
Office of NEPA Policy and Compliance
August 27, 2013105-L Transfer Bay Drainage Repair
CX(s) Applied: B1.3
Date: 08/27/2013
Location(s): South Carolina
Offices(s): Savannah River Operations Office
Modification will provide desired stormwater drainage outside the Transfer Bay (TB) doors, preventing intrusion of water into the TB contamination area.
CX(s) Applied: B1.3
Date: 08/27/2013
Location(s): South Carolina
Offices(s): Savannah River Operations Office
Modification will provide desired stormwater drainage outside the Transfer Bay (TB) doors, preventing intrusion of water into the TB contamination area.