CX-010398: Categorical Exclusion Determination

Power Line Configuration CX(s) Applied: B4.13 Date: 04/25/2013 Location(s): Idaho Offices(s): Idaho Operations Office

Office of NEPA Policy and Compliance

April 25, 2013
Estimated Read Time   min
Power Line Configuration
CX(s) Applied: B4.13
Date: 04/25/2013
Location(s): Idaho
Offices(s): Idaho Operations Office

Based on recommendations by the Idaho National Laboratory (INL) Cultural Resource Management (CRM) Office, the route of the insulated cables on the ground has been changed. This project will install temporary distribution-level power lines between Materials and Fuels Complex (MFC) and Critical Infrastructure Test Range Complex (CITRC) to support research and development and testing using electric power infrastructure.