Boyer-Tillamook Number 1 Transmission Line Access Road MaintenanceCX(s) Applied: B1.3Date: 06/21/2010Location(s): Tillamook County, OregonOffice(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
June 21, 2010CX(s) Applied: B1.3
Date: 06/21/2010
Location(s): Tillamook County, Oregon
Office(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to rebuild and/or repair existing access road and right-of-way (ROW) road in its Eugene Region that provides access to the Boyer-Tillamook Number 1 transmission line and ROW access for sites 3, 4, 6, 7, 9, 12 and 14 between mile/structure 9/3 and 24/5. Project work includes, but is not limited to: reshaping, grading and compacting existing road surfaces and turnouts; hauling, placing, and shaping of aggregate and Riprap; constructing or reconditioning of water bars, drain dips and outlet ditches; watering and compacting subgrade and aggregate; placing geotextile fabric; and cleaning cross drain culverts.