Legacy Pump Removal Supports Hanford West Area Cleanup

Workers at the Hanford Site recently completed one of the most technically demanding pump removal projects in the site’s history, preparing for eventually grouting 200 West Area tank waste. August 4, 2026

Office of Environmental Management

August 4, 2026
Estimated Read Time   min
Video Url
EMTV: Watch the story of how crews successfully finished one of the most technically demanding pump removal projects in Hanford Site history.

RICHLAND, Wash. — Workers at the Hanford Site recently completed one of the most technically demanding pump removal projects in the site’s history, preparing for eventually grouting 200 West Area tank waste.

Installed in Tank SY-101 in 1993 to help reduce hydrogen buildup, the mixer pump is about 50 feet long and weighs roughly 10 tons. Its size and design made the removal a complex but necessary step. Hanford’s only double-shell tank farm in the 200 West Area, SY Farm is expected to play a key role in the next phase of waste cleanup. This pump needed to be removed to install future tank waste retrieval equipment.

“This project was important because it safely removed a large, specialized piece of equipment that had served its purpose and was standing in the way of future work in SY Farm,” said Andy Wiborg, director of the Hanford Field Office Tank Farm Programs Division for the U.S. Department of Energy Office of Environmental Management. “The team carried out this high-hazard work with strong radiological controls, careful planning and disciplined execution.”

A large yellow tank mixer being lowered by a large crane

 

 

 

 

Crews at the Hanford Site removed a legacy mixer pump from Tank SY-101, helping prepare for future waste retrieval and pretreatment work in the 200 West Area.

A large white cylinder shape mixer inside a large waste tank at the Hanford Site

 

 

 

As the mixer pump was removed from the tank, jets on a cleaning system, at right, sprayed high-pressure water to help remove the waste.

The effort required extensive planning, mock-up training and custom engineering. Before work began in the tank farm, crews with contractor Hanford Tank Waste Operations & Closure (H2C) rehearsed the removal at an offsite mock-up to test equipment, refine work steps and improve safety. They also used a specially designed hydraulic lift system, dubbed “Hercules,” to begin freeing the pump in a controlled way. Additional systems were used to clean, handle and package the pump for disposal.

“This project probably touched every department and every organization in the company,” said Jeff Stevens, H2C acting president and program manager. “This truly was a group effort, and everybody should be very proud.”

The crews removed the pump and packaged it for disposal with no contamination issues and no operational upsets, showing how planning, practice and teamwork can support safe progress on Hanford’s cleanup mission.