June 15, 2006

Enforcement Letter, BWXT Y-12 - June 15, 2006

Issued to BWXT Y-12 related to Quality Assurance Deficiencies in construction activities at the Y-12 National Security Complex Highly Enriched Uranium Manufacturing Facility

March 31, 2006

Enforcement Letter, Bechtel BWXT Idaho - March 31, 2006

Issued to Bechtel BWXT Idaho, LLC, related to External Radiation Dosimetry Accreditation Issues at the Idaho National Laboratory

March 16, 2006

Preliminary Notice of Violation, Bechtel National Inc. - EA-2006-03

Issued to Bechtel National Inc., related to Multiple Deficiencies at the Waste Treatment and Immobilization Plant at the Hanford Site

March 7, 2006

Preliminary Notice of Violation, University of Chicago - EA-2006-02

Issued to the University of Chicago related to Nuclear Safety Program Deficiencies at Argonne National Laboratory

February 23, 2006

Preliminary Notice of Violation, University of California - EA-2006-01

Preliminary Notice of Violation issued to the University of California related to Radiological Uptakes, a Radioactive Material Spill, and Radiological Protection Program, Quality Assurance, and Safety Basis Deficiencies at the Lawrence Livermore Nation...

December 16, 2005

Preliminary Notice of Violation, Fluor Hanford Incorporated - EA-2005-07

Issued to Fluor Hanford, Incorporated, related to issues at the Plutonium Finishing Plant and K-Basins facilities at the Hanford Site

December 16, 2005

Preliminary Notice of Violation, UT-Battelle, LLC - EA-2005-06

Issued to UT-Battelle, LLC, related to Facility Hazard Categorization and Safety Basis Compliance Issues at Oak Ridge National Laboratory

August 25, 2005

Preliminary Notice of Violation, Fluor Fernald, Inc. - EA-2005-05

Issued to Fluor Fernald, Inc., related to Radiation Protection and Quality Improvement Deficiencies at the Fernald Environmental Management Project

August 5, 2005

Consent Order, Bechtel Hanford, Inc - EA-2005-01

Issued to Bechtel Hanford, Inc. related to Radiological Uptakes at the 618-2 Burial Ground at the Hanford Site, (Consent Order 2005-1)

August 4, 2005

Preliminary Notice of Violation, Bechtel Jacobs Company, LLC - EA-2005-04

Issued to Bechtel Jacobs Company, LLC, related to the New Hydrofracture Facility Transportation Event and the Personnel Contamination Event at the Hot Storage Garden Facility at the East Tennessee Technology Park