Paducah Demolition and Remediation

PAD_DEACTIVATION_24_0228_1419.JPG

In May 2013, the United States Enrichment Corporation (USEC), a publicly held company that had leased the Paducah Gaseous Diffusion Plant (PGDP) facilities for enrichment operations for the 20 years following the Energy Policy Act of 1992, made the decision to cease enrichment and returned the leased facilities to DOE. DOE and USEC completed the transition and return of the sites process buildings and other facilities in October 2014. Since deactivation activities began, optimization of the site's infrastructure, such as the consolidation of the site’s four switchyards and replacement of its large coal-fired steam plant, continues to ensure the changing needs of the site are being met while reducing future operations and maintenance costs.

When deactivating a process building, there are key priorities Paducah follows. Protecting the workforce, public and environment are the main focuses. The Paducah Site complies with regulations and requirements and allocates decommissioning work to reduce risk. In addition, fulfilling commitments to stakeholders and facilitating low-cost surveillance and maintenance after a facility is deactivated is essential.

MSA 08-04-25(NW).jpg
A material-sizing area worker segments a converter during the deactivation of the Paducah C-333 Process Building.
PAD_MSA_24_0611_8947.JPG
FRNP material-sizing area crews downsize small pieces from a converter shell during segmentation. These smaller pieces are removed to allow the segmented shells to be stacked pending final disposition.

Paducah Cleanup Progress

Since the return of the Paducah Gaseous Diffusion Plant facilities to DOE in October 2014 after 20 years of private operation, the DOE has been able to establish a fully integrated baseline or forecast of time and resources that will be required for the site to be fully remediated. Cleanup of the Paducah Gaseous Diffusion Plant site is anticipated to be completed in 2065 at an approximate total cost of $17 billion.

After the final converter in the C-333 Process Building was segmented in January 2026, crews turned their attention to deactivation activities in the C-337 Process Building. In addition, the highly trained and qualified workforce continues deactivation and remediation activities in other areas of the site to ensure stable operations and continued cost reductions through utility optimization and elimination of maintenance.

Working with the U.S. Environmental Protection Agency and state of Kentucky, the Paducah Site is advancing a holistic approach called Decision 2029, that's consolidating regulator cleanup decisions, allowing for accelerated cleanup and freeing up land at the site for future use as quickly as possible.

  • Deactivation of the C-333 Process Building began in 2019. In preparation for demolition, nearly 500 pieces of large process gas equipment called converters were downsized in the Material-Sizing Area. This was completed in early 2026. The MSA was specifically constructed to complete segmentation, analyze non-destructive assay measurements and downsize materials safely.

By the Numbers

By The Numbers 2025 Paducah_Final.jpg

 

 

 

 

 

From square feet of buildings demolished to gallons of groundwater treated and more, check out By the Numbers for the Paducah Site.