Paducah Demolition and Remediation

PAD_DEACTIVATION_24_0228_1419.JPG

In May 2013, the United States Enrichment Corporation (USEC), a publicly held company that had leased the Paducah Gaseous Diffusion Plant (PGDP) facilities for enrichment operations for the 20 years following the Energy Policy Act of 1992, made the decision to cease enrichment and returned the leased facilities to DOE. DOE and USEC completed the transition and return of the sites process buildings and other facilities in October 2014. Since deactivation activities began, optimization of the site's infrastructure, such as the consolidation of the site’s four switchyards and replacement of its large coal-fired steam plant, continues to ensure the changing needs of the site are being met while reducing future operations and maintenance costs.

When deactivating a process building, there are key priorities Paducah follows. Protecting the workforce, public and environment are the main focuses. The Paducah Site complies with regulations and requirements and allocates decommissioning work to reduce risk. In addition, fulfilling commitments to stakeholders and facilitating low-cost surveillance and maintenance after a facility is deactivated is essential.

MSA 08-04-25(NW).jpg
A material-sizing area worker segments a converter in support of continued deactivation of the Paducah C-333 Process Building.

Deactivation work on the C-333 Process Building continues with a focus on the safe removal and segmentation of its large components. In addition, PPPO is planning to begin the deactivation of another former enrichment process building, C-331. D&R activities will continue on surplus ancillary facilities, such as former cooling towers, helping to ensure a stable, highly trained and qualified workforce remains available.

PAD_MSA_24_0611_8947.JPG
FRNP material-sizing area crews downsize small pieces from a converter shell during segmentation. These smaller pieces are removed to allow the segmented shells to be stacked pending final disposition.

Paducah Cleanup Progress

Since the return of the Paducah Gaseous Diffusion Plant facilities to DOE in October 2014 after 20 years of private operation, the DOE has been able to establish a fully integrated baseline or forecast of time and resources that will be required for the site to be fully remediated. Cleanup of the Paducah Gaseous Diffusion Plant site is anticipated to be completed in 2065 at an approximate total cost of $17 billion.

  • Since 2019, deactivation of the C-333 Process Building continues. To prepare for building demolition, more than 500 pieces of large process gas equipment called converters are being removed and downsized at the Material-Sizing Area. The Material-Sizing Area is an area specifically constructed to complete segmentation, analyze non-destructive assay measurements and downsize materials safely. In 2023, this area was constructed when the removal process in C-333 began clearing process gas equipment, housings and concrete pedestals. Progress is accelerated by utilizing lessons learned from the Portsmouth Site and utilized feedback to improve both safety and production.

By the Numbers

By The Numbers 2025 Paducah_Final.jpg

 

 

 

 

 

From square feet of buildings demolished to gallons of groundwater treated and more, check out By the Numbers for the Paducah Site.