Line Tap Construction on the East Ellensburg Tap to Columbia-Ellensburg Transmission Line CX(s) Applied: B4.6 Date: 04/11/2014 Location(s): Washington, Washington Offices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
April 11, 2014Line Tap Construction on the East Ellensburg Tap to Columbia-Ellensburg Transmission Line
CX(s) Applied: B4.6
Date: 04/11/2014
Location(s): Washington, Washington
Offices(s): Bonneville Power Administration
Bonneville Power Administration proposes to build a tap on its East Ellensburg Tap to Columbia-Ellensburg 115-kilovolt transmission line to connect the City of Ellensburg’s new Helena Avenue Substation in East Ellensburg, Washington.
CX(s) Applied: B4.6
Date: 04/11/2014
Location(s): Washington, Washington
Offices(s): Bonneville Power Administration
Bonneville Power Administration proposes to build a tap on its East Ellensburg Tap to Columbia-Ellensburg 115-kilovolt transmission line to connect the City of Ellensburg’s new Helena Avenue Substation in East Ellensburg, Washington.