Fiber Installation at Snohomish, SnoKing and Murray Substations CX(s) Applied: B4.7 Date: 01/27/2014 Location(s): Washington Offices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
January 27, 2014Fiber Installation at Snohomish, SnoKing and Murray Substations
CX(s) Applied: B4.7
Date: 01/27/2014
Location(s): Washington
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to install short sections of new fiber optic cable at three substations in Snohomish County to support a request from Snohomish Public Utility District (PUD). The PUD currently owns control and communication equipment at BPA’s Snohomish, SnoKing, and Murray substations.
CX(s) Applied: B4.7
Date: 01/27/2014
Location(s): Washington
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to install short sections of new fiber optic cable at three substations in Snohomish County to support a request from Snohomish Public Utility District (PUD). The PUD currently owns control and communication equipment at BPA’s Snohomish, SnoKing, and Murray substations.